Things may be a little delayed with CA-2.
The aircraft itself is fine.
The issue is the fact that fuselage 179, right in front of us that is destined for Dover AFB, was delayed coming off the production line by two weeks. This has had an obvious downstream impact on our aircraft, fuselage 180.
That being said, Boeing is doing their damndest to get us our aircraft as quickly as possible.
CA-2 flew it's first airborne, production test flight yesterday, Friday 5th Oct.
We're a few days behind schedule, but no cause for alarm just yet.
We had a minor snag shortly after takeoff, returned, fixed and then went airborne again.
Right now looks as if we'll slide a day or two to the right and be a little late for delivery.
In the big scheme of things - it's still "all good".
Even if we're a day or two late, by letter of the contract Boeing is still early with its delivery and providing us with excellent customer service.